Final Dogger Bank substation installed
Final offshore substation has been installed for 3.6 GW Dogger Bank wind farm as commissioning phase begins, with full operations expected by late 2025.
Final offshore substation has been installed for 3.6 GW Dogger Bank wind farm as commissioning phase begins, with full operations expected by late 2025.
SSE Renewables has warned further delays to turbine installation at the 1.2 GW Dogger Bank A wind farm off east England may push back full operations to 2025.
UK: Hareema Marine Contractors is to install the offshore substation topside at Dogger Bank A offshore wind farm construction site in the UK’s North Sea.