EnergyConnect begins power transmission in the west
EnergyConnect has reached a major milestone, with electricity now flowing for the first time through its western section, marking a new chapter in Australia’s energy transformation.
EnergyConnect has reached a major milestone, with electricity now flowing for the first time through its western section, marking a new chapter in Australia’s energy transformation.
Construction of the South Australian part of Project EnergyConnect, the new high-voltage transmission line between South Australia and New South Wales, has been completed.
ElectraNet announced that the South Australian portion of the EnergyConnect project has neared completion.
ElectraNet has proposed network upgrades to meet new and existing customer power demand.
Australia, Eyre Peninsula: The construction of a new 270 km, HV transmission line across the Eyre Peninsula is underway, carried out by ElectraNet and Downer.
ElectraNet’s Davenport substation, near Port Augusta, has received its first of two synchronous condensers for installation.