MORE’s 43.2 MW wind farm in Greece begins operations
Motor Oil Renewable Energy’s 43.2 MW wind power plant near North Macedonia border enters regular operation.
Motor Oil Renewable Energy’s 43.2 MW wind power plant near North Macedonia border enters regular operation.
North Macedonia’s transmission system operator MEPSO has put a 400/110 kV transformer at the Transformer Station (TS) Manastir 2 into full operation.
Cosmatos Group coordinated the transport of a 240 T transformer from Greece to North Macedonia.
North Macedonia, Ohrid: The works on the construction of a new 400/110 kV substation Ohrid have officially commenced.
North Macedonia’s transmission system operator and Croatia’s Dalekovod have signed a $3.8 M contract on the reconstruction of the 400 / 110 kV Bitola 2 substation.
Macedonia’s (TSO) MEPSO operator has signed deals for a new line to connect with Albania, a new substation near Ohrid and an extension of Bitola 2 substation.